← Project map

Mersing

M&E Installation for Leachate Treatment Plant, Mersing

Integrated mechanical & electrical installation, electrical control switchgear and activated carbon & sand filtration units in Mersing.

Client
National Solid Waste Management Dept (JPSPN)
Contract value
RM 3,536,888.00
Duration
33 Weeks
Status
Target completion 2027

Site scope

At the Mersing disposal site, the contract covers mechanical and electrical installation for the leachate treatment plant. The photos show the interface between filtration equipment, pipework and electrical controls.

Site photos

Activated carbon and sand filtration vessels with piping.
Activated carbon and sand filtration vessels with piping.
Main electrical switchgear and control panel inspection at Mersing.
Main electrical switchgear and control panel inspection at Mersing.
Outdoor control enclosure at the Mersing treatment plant.
Outdoor control enclosure at the Mersing treatment plant.

SSB GROUP · SENTRATEK SDN BHD

M&E Installation for Leachate Treatment Plant, Mersing

Mersing

Client
National Solid Waste Management Dept (JPSPN)
Contract value
RM 3,536,888.00
Duration
33 Weeks
Status
Target completion 2027

Integrated mechanical & electrical installation, electrical control switchgear and activated carbon & sand filtration units in Mersing.

Activated carbon and sand filtration vessels with piping.
/en/projects/ltp-mersing

SSB GROUP · RFQ

Request Quotation & Official Enquiry

Select a service and describe your requirements. Keep your enquiry reference for follow-up.

Call +603-6178 5849